Punjab and Haryana High Court
Decided on : 14.07.2022

Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Section 58 – Interest on delay possession -- Delay due to non-issuance of occupancy certificate – Ground of -- Apartment-buyer held entitled to interest for the delayed delivery of possession of the apartment – Contention of the appellant that the project was completed within the time prescribed, however, the government did not issue the occupancy certificate to the promoter – Held, This is a matter between the appellant and the government, apartment-buyer cannot be penalized for the same – Appeal dismissed.

(Para 2-6)