Please Log in / Register to access the full text of this judgment and the entire database

Supreme Court of India
Decided on: 20.01.2023

Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (30 of 2013), Section 24(2) -- Lapse of acquisition proceedings initiated under the Land Acquisition Act, 1894 -- Possession by Panchnama and Possession report – Permissibly of -- High Court declared that the acquisition proceedings initiated under the Land Acquisition Act, 1894 lapsed u/s 24(2) of 2013 Act – Held, impugned judgment and order is contrary to the law laid down in the Constitution Bench decision, Indore Development Authority’s case (2020) 8 SCC 129 = (2020) Law Today Live Doc. Id. 15233 -- Possession of the land in question taken over by the DDA through LAC/ L&B Department by drawing the panchnama and preparing the possession report, which is permissible -- Impugned judgment and order set aside.

(Para 1-5)