Search By Topic: Consumer Law/ RERA

2. (P&H) 22-11-2023

A. Punjab Regional and Town Planning and Development Act, 1995 (11 of 1995), Section 45 – Residual claim left over by RERA – Maintainability of revision before Government -- When the respondent left aside the residual claims and restricted her prayers in consonance with the provisions of the RERA Act only, specifically u/s  18 thereof, then it could be said that filing of revision petition before the Government u/s 45 of the PRTPD Act was the only appropriate alternative remedy -- No challenge to the order passed by the Chief Administrator, PUDA was made as projected by the appellant -- Such objection was neither taken by the appellant before the Authority nor before the Appellate Tribunal and was raised for the first time at this belated stage only does not hold any substance and therefore, challenge on this ground cannot be sustained.

(Para 14)

B. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Section 2(zk) – Promoter – Development Authority -- Definition of promoter explicitly covers “Development Authority”, therefore, there remains no doubt that appellant was very well covered within the ambit of promoter as stipulated under the RERA Act.

(Para 16)

C. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Section 18 -- Delay in possession – Interest for delayed period -- Basic amenities – Requirement of – “as is where is” basis – Effect of -- Appellate Tribunal held respondent entitle to interest on delayed possession -- If on account of presence of this clause in the allotment letter, appellant could be absolved of any liability, then there was no need for it to invest its resources and time in this work -- “development work” was the responsibility of the appellant -- Mere physical possession without any basic amenities would serve no purpose as to carry out construction work and commercial activity over the site in question, the respondent required all necessary basic amenities -- To start the construction work at a site, many machineries require supply of electricity which was a basic amenity, therefore, Appellate Tribunal rightly held that the sites were ready for possession on 19.10.2017 only -- No concession can be claimed by the appellant/ Development Authority being State in comparison to a private promoter -- Order passed by the Appellate Tribunal, upheld.

(Para 2, 17-23)

5. (SC) 31-07-2023

A. Consumer Protection Act, 1986 (68 of 1986), Section 12 -- Second complaint -- Withdrawal of the earlier complaint – Bar to second complaint -- Having not argued, before the State Commission, the point of the present complaint being barred in view of the withdrawal of the earlier complaint, the National Commission was not justified, in allowing the respondent-Insurance Company to urge that point therefrom.

(Para 5)

B. Consumer Protection Act, 1986 (68 of 1986), Section 12 – Code of Civil Procedure, 1908 (V of 1908), Order 23 Rule 1(4) -- Theft of vehicle --Withdrawal of the complaint – Maintainability of second complaint – Complaint filed after theft due to non-settlement of claim by the Insurance Company -- Repudiation of the claim was made during the pendency of the said complaint -- Complaint withdrawn by the advocate on the pretext of the case being prolonged by the advocate of the Insurance Company, without having express instructions for withdrawal of the said complaint -- For the fault of the advocate, the complainant cannot be made to suffer -- Complaint cannot be thrown out on the threshold of Order XXIII Rule (1)(4) CPC and in the peculiar facts, it requires consideration on merits.

(Para 8)

C. Insurance law -- Theft of vehicle -- Repudiation of claim -- No-standard claim -- Vehicle left unattended by driver with keys inside -- It is not the case of the Insurance Company that the Claimant consented or connived in the removal of the vehicle, would not be theft, in the eye of law -- Time gap between the driver alighting from the vehicle and noticing the theft, is very short as is clear from the facts of the case -- It was not a fundamental breach of Condition warranting total repudiation -- 75% ought to have been awarded on a non-standard basis.

(Para 11-16)

8. (J&K&L) 12-06-2023

A. Consumer Protection Act, 1986 (68 of 1986), Section 12 -- Insurance claim – Damage to tractor in fire incident -- Tractor cannot be restricted in its use only within the purchaser’s premises -- When the tractor-in-question got damaged in a fire incident it was actually employed in agricultural pursuits -- Insurance cover specifically provides that the policy does not cover use of tractor for organized racing, pace making, reliability trails and speed testing -- Tractor-in-question was not being used for any such thing at the time of incident -- Further, the insurance certificate specifically covers the fire allied perils; therefore, the insurance company cannot be absolved of its liability to indemnify the insured.

(Para 7)

B. Consumer Protection Act, 1986 (68 of 1986), Section 12 -- Insurance claim -- Commercial use of tractor – Violation of terms and conditions of insurance policy -- Evidence -- Contention that at the time of incident the tractor-in-question was being used for threshing the wheat of one SS on hire and reward purposes, which was against and in violation of the terms and conditions of the insurance policy -- Wife sworn an affidavit specifically deposing that his deceased husband had sold the standing wheat crop to claimant and said claimant was threshing the same being his personal property when the incident of fire had taken place -- Nine more witnesses have deposed the same thing -- Thus, it cannot be said that claimant was using his tractor for hire and reward purposes -- Award of rupees four lacs on 08.06.2012 and till now more than eleven years have elapsed -- Awarded amount shall carry 6% interest from the date of filing of the complaint.

(Para 8)

12. (SC) 09-02-2023

A. Consumer Protection Act, 1986 (68 of 1986), Section 23 – Long time in decision -- NCDRC took in excess of 10 (ten) months to dismiss the complaint after it reserved the same for passing orders – Held, long delay in passing the order on the complaint did have its own effect on the ultimate decision of the NCDRC.

(Para 8)

B. Consumer Protection Act, 1986 (68 of 1986), Section 2(1)(r), 23 -- Unfair trade practice -- Non-providing of amenities by builder -- It was the duty of the NCDRC to ascertain, based on the materials on record, whether if at all and to what extent facilities and amenities as promised were offered and/or whether there was any deficiency of service – Once the NCDRC arrived at a finding that the respondents were casual in their approach and had even resorted to unfair trade practice, it was its obligation to consider the appellants’ grievance objectively and upon application of mind and thereafter give its reasoned decision – Matter remanded back to NCDRC.

(Para 8-12, 20)

C. Consumer Protection Act, 1986 (68 of 1986), Section 2(1)(r) -- Unfair trade practice -- Non-providing of amenities by builder – Registration of sale deed – Forfeiture of rights – Appellants had not forfeited any right by registration of the sale deeds and if indeed the respondents were remiss in providing any of the facilities/ amenities as promised in the brochure/ advertisement, it was the duty of the NCDRC to set things right.

(Para 12)

D. Consumer Protection Act, 1986 (68 of 1986), Section 2(1)(r) -- Kolkata Municipal Corporation Act, 1980 (LIX of 1980), Section 393, 394, 403 -- Calcutta Municipal Corporation Buildings Rules, 1990, Rule 26 --  Completion certificate – It is the obligation of the person intending to erect a building or to execute works to apply for completion certificate -- It is no part of the flat owner’s duty to apply for a completion certificate – Respondents/ builder have been let off by the NCDRC in a manner contrary to law – Matter remitted back to NCDRC.

(Para 17-20)

E. Consumer Protection Act, 1986 (68 of 1986), Section 2(1)(r), 23 -- Unfair trade practice -- Compensation -- Appellants failed to give detailed particulars and have also been on the wrong side of law by taking possession of their respective flats without the completion certificate, that chapter closed

(Para 21)

18. (SC) 10-11-2022

A. Consumer Protection Act, 1986 (68 of 1986), Section 2(1)(d)(ii) -- Consumer -- Appellant availed services provided by the respondent Nos. 1 to 3 and respondent No. 4 is a beneficiary of such services, therefore the appellant would fall under the definition of a ‘consumer’ as is under Section 2(1)(d)(ii) of the Act of 1986.

(Para 33)

B. Letter of credit -- A letter of credit is a document issued by a bank (issuing bank) on behalf of a party (applicant) in favour of another party (beneficiary) under which, the issuing bank undertakes to pay to the beneficiary, certain sums of money subject to compliance of the terms and conditions of the letter of credit.

(Para 34)

C. Letter of credit -- In an international transaction, the beneficiary is the seller who requests the applicant (buyer) to furnish a letter of credit from any bank which is recognized worldwide (issuing bank) -- Letter of credit is issued in favour of a beneficiary on the request of an applicant after furnishing securities as may be demanded by the issuing bank -- A seller can ask the issuing bank to honour the letter of credit to his own bank (confirming bank) within a certain maturity date -- Seller is required to produce certain documents regarding proof of delivery of goods, commercial invoice, bill of lading, insurance documents etc. before the confirming bank -- On scrutiny the confirming bank would ask for advice of the issuing bank to confirm whether the documents produced by the beneficiary is compliant to the terms and conditions of the letter of credit -- Once the issuing bank confirms the document, the confirming bank is obligated to pay to the beneficiary on demand, the credit amount and in turn recover the same from the issuing bank.

(Para 34)

D. Consumer Protection Act, 1986 (68 of 1986), Section 2(g), 17 -- Letter of credit -- Deficiency in service – Despite clear instructions, respondent Nos. 1 to 3 negligently recorded the port of loading to be JNPT Bombay -- It is due to this negligence as well as deficiency in service of the respondent Nos. 1 to 3 that the respondent No. 4 Bank refused to accept/honour the documents including the FCR and the same was returned to the bank of the appellant – Due to refusal of honouring the said documents, the sale consideration was not paid to the appellant who suffered loss as well as mental harassment and agony -- National Commission vide impugned order has reduced the amount of compensation to Rs.10,000/- as against the amount granted by the State Commission to be paid to the appellant i.e., a sum of Rs.13,79,901/-, together with compensation of Rs.50,000/- and cost of litigation amounting to Rs.10,000/- – Appeal allowed, impugned judgment and order passed by the National Commission set aside and the judgment and order passed by the State Commission restored.

(Para 3, 36-41)

19. (SC) 09-11-2022

A. Insurance Regulatory and Development Authority (Protection of Policyholders' Interests) Regulations, 2002, Clause 3(ii), 3(iv) – Exclusion clause in insurance policy – Disclosure/ Notice to insured --  It is the foremost duty of the insurer to give effect to a due disclosure and notice in its true letter and spirit – Non-disclosure and a failure to furnish a copy of the said contract by following the procedure required by statute, would make the said clause redundant and non-existent -- Any non-compliance would take away their right to plead repudiation of contract by placing reliance upon any of the terms and conditions included thereunder.

(Para 15, 42)

B. Insurance Regulatory and Development Authority (Protection of Policyholders' Interests) Regulations, 2002, Clause 3(ii), 3(iv) -- Insurance policy – Duty of insurance company -- Insurer and his agent are duty bound to provide all material information in respect of a policy to the insured – If proposal form is not filled by the insured, a certificate has to be incorporated at the end of the said form that all the contents of the form and documents have been fully explained to the insured and made him to understand – It is duty upon the insurer to furnish a copy of the proposal form within thirty days of the acceptance, free of charge -- Any non-compliance, offending clause, be it an exclusion clause, cannot be pressed into service by the insurer.

(Para 21)

C. Doctrine of Blue Pencil --  Insurance policy – Offending clauses -- Doctrine of “blue pencil” which strikes off the offending clause being void ab initio, has to be pressed into service – Said clause being repugnant to the main contract, and thus destroying it without even a need for adjudication, certainly has to be eschewed by the Court, requires an effacement in the form of declaration of its non-existence, warranting a decision by the Court accordingly.

(Para 22)

D. Consumer Protection Act, 1986 (68 of 1986), Section 12, 17, 21 -- Consumer – Plaintiff in a suit -- Consumer under C.P. Act, 1986 is at an elevated place than the plaintiff in a suit -- A dispute before the Consumer Commission is to be seen primarily from the point of view of the consumer as against the civil suit -- It is only to avoid any possible bottleneck in granting the relief.

(Para 28)

E. Consumer Protection Act, 2019 (35 of 2019), Section 2(46)(47), 47, 49 58, 59 -- Unfair contract – Unfair trade practice – Power of State Commission/ National Commission -- Section 47 and 58 of the 2019 Act have been introduced to facilitate the State Commission and the National Commission to exercise jurisdiction over a contract which is unfair – The power is not only with respect to identifying a contract as unfair or not, but also to grant the consequential relief -- Under sub-section (2) of Section 49 and 59 of the 2019 Act, the State Commission and the National Commission, respectively, may declare any terms of the contract being unfair to any consumer to be null and void -- In these provisions, there exists ample power to declare any terms of the contract as unfair by the State Commission and the National Commission – Consequence of the declaration of that term as unfair, would make the contract active and executable to the benefit of the consumer -- Therefore, this provision takes care of a possible mischief by the insurer as against the consumer.

(Para 29-34)

F. Insurance Regulatory and Development Authority (Protection of Policyholders' Interests) Regulations, 2002, Clause 3(ii), 3(iv) –– Exclusion clause in Insurance policy -- Unfair contract -- Both the forums concurrently held that respondent No. 1/ Insurer was conscious of the fact that the contract was entered into for insuring a shop situated in the basement -- Even as per the common law principle of acquiescence and estoppel, respondent No. 1/ Insurer  cannot be allowed to take advantage of its own wrong, if any -- Non-compliance of Clauses (3) and (4) of the IRDA Regulation, 2002 preceded by unilateral inclusion, and thereafter followed by the execution of the contract, receiving benefits, and repudiation after knowing that it was entered into for a basement, would certainly be an act of unfair trade practice.

(Para 37-39)

27. (SC) 07-04-2022

A. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Section 1 -- Consumer Protection Act, 1986 (68 of 1986), Section 1 --  Interpretation of statute – RERA Act – Consumer Act – Both Acts neither exclude nor contradict each other and they must be read harmoniously to subserve their common purpose.

(Para 1)

B. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Section 18 -- Consumer Protection Act, 1986 (68 of 1986), Sections 14, 23 -- Apartment Buyer’s Agreement – One-sided clauses – Refund of amount with interest – Right of -- Commission is correct in its approach in holding that the clauses of the agreement are one-sided and that the Consumer is not bound to accept the possession of the apartment and can seek refund of the amount deposited by her with interest.

(Para 10)

C. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Section 18 -- Consumer Protection Act, 1986 (68 of 1986), Sections 14, 23 -- Consumer Protection Act and the RERA Act neither exclude nor contradict each other -- They are concurrent remedies operating independently and without primacy – When Statutes provide more than one judicial fora for effectuating a right or to enforce a duty-obligation, it is a feature of remedial choices offered by the State for an effective access to justice -- While interpreting statutes provisioning plurality of remedies, it is necessary for Courts to harmonise the provisions in a constructive manner – A consumer invoking the jurisdiction of the Commission can seek such reliefs as he/she considers appropriate -- A consumer can pray for refund of the money with interest and compensation -- Consumer could also ask for possession of the apartment with compensation -- Consumer can also make a prayer for both in the alternative -- Position is similar to the mandate u/s of the RERA Act -- Freedom to choose the necessary relief is of the Consumer and it is the duty of the Courts to honour it.

(Para 11, 19)

D. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Section 18 -- Consumer Protection Act, 1986 (68 of 1986), Sections 14, 23 -- Refund of amount with interest -- Consumer prayed for the solitary relief for return of the amount paid towards purchase of the apartment without a prayer for alternate relief –Commission correctly exercises its power and jurisdiction in passing the directions for refund of the amount with interest -- Interest payable on the amount deposited to be restitutionary and also compensatory, interest has to be paid from the date of the deposit of the amounts -- Commission in the order impugned has granted interest from the date of last deposit – Held, this does not amount to restitution – Direction given that the interest on the refund shall be payable from the dates of deposit -- Interest of 9 per cent granted by the Commission is fair and just.

(Para 18-22)

34. (P&H) 27-11-2020

A. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Section 4(2)(l)(C), 5(3) – Interpretation of Statute -- Declaration by promoter -- Registration of Real Estate Project – Validity of -- It is settled law that while interpreting a Statute, its plain meaning must be given effect to in case there is no ambiguity -- A perusal of sub-section 3 of Section 5 of the Act leaves no manner of doubt that registration granted u/s 5 of the Act shall be valid for a period declared by the promoter u/s 4(2)(l)(C) -- This is the plain and clear meaning of the words used therein -- Thus, no other interpretation is possible.

(Para 9)

B. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Section 5 – Registration of project – Refusal by Authority – Opportunity of hearing – Authority has the power either to register a project or to refuse registration but before refusal, an opportunity of hearing must be granted -- There could be many reasons for refusing to register a project and one of them could be an arbitrary time period mentioned in the declaration -- During the course of hearing, the promoter would be in a position either to justify the period or to accept the objections of the Authority and modify the period.

(Para 10)

C. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Section 5 – Registration of project -- Declaration by promoter – Reduction in time -- Power/ Jurisdiction of Authority --- Authority has no power or jurisdiction to reduce the time period mentioned in the declaration -- If it feels that the period mentioned is arbitrary or unacceptable due to any reasons, a notice to show cause for rejection of the application must be given.

(Para 13)

35. (SC) 02-11-2020

A. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Section 71(1) -- Consumer Protection Act, 1986 (68 of 1986), Section 12, 17, 21, 23 -- Pending complaints before Consumer Forums/Commission – RERA came into force – Effect on complaints -- Proviso of Section 71(1) gives a right or an option to the concerned complainant but does not statutorily force him to withdraw such complaint nor do the provisions of the RERA Act create any mechanism for transfer of such pending proceedings to authorities under the RERA Act.

(Para 28)

B. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Section 18, 79, 88 -- Consumer Protection Act, 1986 (68 of 1986), Section 12, 17, 21, 23 -- Consumer complaint after coming into force of RERA Act – Maintainability of -- Cases where such proceedings under the CP Act are initiated after the provisions of the RERA Act came into force, there is nothing in the RERA Act which bars such initiation -- Absence of bar u/s 79 to the initiation of proceedings before a fora which cannot be called a Civil Court and express saving u/s 88 of the RERA Act, make the position quite clear -- Further, Section 18 itself specifies that the remedy under said Section is “without prejudice to any other remedy available” -- Thus, the parliamentary intent is clear that a choice or discretion is given to the allottee whether he wishes to initiate appropriate proceedings under the CP Act or file an application under the RERA Act.

(Para 28)

C. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Section 18 – Buyer-seller agreement – Registration under RERA Act -- Effect of -- Construction was to be completed in 42 months -- Period had expired well before the Project was registered under the provisions of the RERA Act – Held, merely because the registration under the RERA Act is valid till 31.12.2020 does not mean that the entitlement of the concerned allottees to maintain an action stands deferred -- For the purposes of Section 18, the period has to be reckoned in terms of the agreement and not the registration -- Entitlement of the Complainants must be considered in the light of the terms of the Builder Buyer Agreements.

(Para 33)

36. (P&H) 16-10-2020

A. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Section 43(5) – Proviso for pre-deposit in appeal – Challenge to -- Requirement of pre-deposit of the amount, as set out in the proviso to Section 43 (5) of the Act, cannot be held to be unreasonable or arbitrary -- Challenge to the proviso to Section 43 (5) of the Act must fail -- Prayer in that regard rejected.

(Para 12)

B. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Sections 43(5), 44 -- Proviso for pre-deposit in Appeal – Sections 43 and 44 of the Act are to be read harmoniously -- There to be no inconsistency in the wording of Section 43 (5) and Section 44 of the Act -- An appeal filed by the promoter, the requirement under the proviso to Section 43 (5) of the Act, will have to be mandatorily fulfilled, even for the purposes of the Appellate Tribunal having to pass orders in terms of Section 44 of the Act -- Proviso to Section 43 (5) of the Act clearly states that the pre-deposit is required to be made “before the said appeal is heard.” -- Appellate Tribunal is not obliged to proceed to ‘entertain’ or hear an appeal that has been filed before it, if the promoter, who has filed such appeal, fails to comply with the direction for making the pre-deposit in terms of the proviso to Section 43 (5) of the Act.

(Para 14)

C. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Sections 43(5), 44 -- Proviso for pre-deposit in appeal – Waiver of – Appellate Tribunal has no power to waive the requirement of the making of a pre-deposit as mandated by the proviso to Section 43 (5) of the Act.

(Para 15)

D. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Sections 43(5), 44 -- Proviso for pre-deposit in appeal – Release of – All the appeals before it, the Appellate Tribunal would order the placing of the pre-deposit amount in a fixed deposit pending the final decision in the appeal – If it were to order release of the whole or part of the amount to the allottee, that would have to be upon the furnishing of adequate security – This would be necessary as in the event of the appellant succeeding, the amount pre-deposited would be required to be refunded.

(Para 23)

E. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Sections 4(2)(i)(C), 18(1)(2)(3), 19 (4) – Delay in possession – Remedy for allottee – Section 19 (4) of the Act states that in the event of a promoter failing to comply or being unable to give possession of the apartment, plot or building in accordance with the terms of agreement for sale or due to discontinuance of his business as a developer on account of suspension or revocation of his registration under the provisions of this Act or the rules or regulations made thereunder, the allottee shall be entitled: (a) to claim refund of the amount paid along with interest at such rate as has been prescribed; and (b) the compensation in the manner provided under the Act – To that extent Section 19 (4) of the Act can be said to be a ‘mirror provision’ of Section 18 (1) to (3) of the Act -- Both these provisions recognize a right of an allottee to distinct remedies, viz., refund of the amount together with interest, interest for delayed handing over of possession and compensation.

(Para 35)

F. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Section 31 – Jurisdiction/ Power of RERA Authority/ Adjudicating officer --  Complaints can be filed either with the Authority or the AO for violation or contravention of the provisions of the Act or the Rules and Regulations -- Such complaint can be filed against “any promoter, allottee or real estate agent”, as the case may be -- Such complaint can be filed by “any aggrieved person” -- The Explanation to Section 31 (1) of the Act states that for the purposes of said sub-section “person” shall include an association of allottees or any voluntary consumer association registered under any law for the time being in force.

(Para 36)

G. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Sections 34(f), 35(1)(2) – Functions/ Power of Power of RERA Authority -- Section 34 (f) of the Act states that the functions of the Authority shall include ensuring “compliance of its regulations cast upon the promoters, the allottees and the real estate agents under this Act and the rules and regulations made thereunder” – U/s 35 of the Act the Authority can, either on a complaint or suo moto by an order, call upon any promoter or allottee or real estate agent to furnish in writing such information or explanation relating to its affairs as the Authority may require – U/s 35(1) Authority can appoint one or more persons to make an inquiry into the affairs of any promoter or allottee or the real estate agent, as the case maybe – U/s 35 (2) of the Act, the Authority is given all the powers vested in a civil court under the Code of Civil Procedure, 1908 while trying a suit and this includes the discovery and production of books of account and other documents; summoning and enforcing the attendance of persons and examining them; issuing commissions for the examination of witnesses or documents and “any other matter which may be prescribed.”

(Para 37, 38)

H. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Sections 36, 37 -- Enquiry by RERA Authority – Power of – Scope of -- Section 36 of the Act recognizes the power of the authority during an inquiry, to make interim orders restraining any promoter, allottee or real estate agent from carrying on any act in contravention of the Act, until the conclusion of such inquiry and without giving notice to such party, where the Authority deems it necessary -- Section 37 of the Act is widely worded and states that the Authority may, for the purpose of discharging its functions under the Act or Rules or Regulations “issue such directions from time to time, to the promoters or allottees or real estate agents, as the case may be, as it may consider necessary” and such directions shall be binding on all concerned.

(Para 39)

I. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Section 38 -- Penalty and interest – Power of RERA Authority -- Section 38 talks about the power of the Authority to impose penalty or interest, in regard to any contravention of obligations cast upon the promoters, the allottees and the real estate agents.

(Para 40)

J. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Sections 31, 34(f), 35, 36, 37, 38, 71 -- Power of RERA Authority/ Adjudicating officer – Plea that the power and scope of the functions of the Authority are limited to determining penalty or interest u/s 38 of the Act is rejected as it overlooks the wide range of powers of the Authority on a collective reading of Sections 31, 34 (f), Sections 35, 36 and 37 -- Power to issue interim orders u/s 36 of the Act and the power to issue directions u/s 37 of the Act are not made available to the AO u/s 71 of the Act -- Powers of the Authority u/s 35 of the Act are also of a wide nature -- While discharging those functions, it will be open to the Authority to even require the AO to conduct the inquiry -- Section 35 (2) of the Act also makes its plain that the Authority will have the same powers as a civil Court -- Legislative intent is, therefore, not to diminish the adjudicatory functions of the Authority but rather to provide it with all the trappings of a quasi-judicial/judicial authority while inquiring into the complaints and issuing directions.

(Para 61, 62)

K. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Sections 31, 34(f), 35, 36, 37, 71, 72 – Refund of amount – Compensation and interest -- Jurisdiction  of RERA Authority/ Adjudicating officer – Act does use distinct expressions like ‘refund’, ‘interest’, ‘penalty’ and ‘compensation’, a collective reading of the provisions makes it apparent that when it comes to refund of the amount, and interest on the refund amount, or directing payment of interest for delayed delivery of possession, or penalty and interest thereon, it is the Authority which has the power to examine and determine the outcome of a complaint -- Expression ‘interest’ as used in Section 18 of the Act is a pre-determined rate, as may be fixed by the government, and is distinct from the interest by way of compensation that has to be computed by the AO in terms of Section 71 (3) keeping in view the factors outlined in Section 72 of the Act -- When it comes to the question of seeking the relief of compensation or interest by way of compensation, the AO alone has the power to determine it on a collective reading of Sections 71 and 72 of the Act -- If Sections 71 and 72 of the Act are read together, it is plain that the AO has to adjudge the ‘quantum of compensation’.

(Para 63, 64)

L. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Sections 31, 34(f), 35, 36, 37, 71, 88 – Refund of amount – Compensation and interest -- Jurisdiction  of RERA Authority/ Adjudicating officer – Pendency of Consumer Complaint – Effect upon -- It is not mandatory for a person, who has a complaint before the consumer fora to have his complaint transferred to the AO -- He can pursue both the remedies simultaneously on the strength of Section 88 of the Act -- If, however, such person opts to withdraw his complaint before the consumer fora to come to the AO, the scope of the relief he seeks would be limited to the compensation or interest -- He will, therefore, have to take a conscious decision -- If the relief he is seeking in the complaint before the consumer fora is in addition to seeking compensation or interest in the form of compensation, for instance refund of the amount and interest thereon, then he will have to take a conscious decision on restricting his relief before the AO to one of compensation or interest by way of compensation -- For the remaining reliefs, he will have to go before the Authority.

(Para 65)

M. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Sections 12, 14, 18, 19 – Haryana Real Estate (Regulation and Development) Rules, 2017, Rule 29 -- Compensation or interest by way of compensation -- If a complainant is seeking only compensation or interest by way of compensation simpliciter with no other relief, then obviously the complainant would straightway file a complaint before the AO -- Complaint will be filed in form CAO and will be referrable to Rule 29 of the Haryana Rules -- AO in such instance would proceed to determine whether there is a violation of Sections 12, 14, 18 and 19 of the Act.

(Para 66)

N. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Sections 12, 14, 18, 19, 35, 36, 37, 71, 72 -- Compensation and payment of interest – Power of RERA Authority/ Adjudicating officer -- Single complaint seeking a combination of reliefs with one of the reliefs being relief of compensation and payment of interest -- In such instance, the complaint will first be examined by the Authority which will determine if there is a violation of the provisions of the Act -- If such complaint is by the allottee and against the promoter and if the Authority comes to an affirmative conclusion regarding the violations it will then, for the limited purpose of adjudging the quantum of compensation or interest by way of compensation, refer the complaint for that limited purpose to the AO -- With the Authority already having found in favour of the complainant as regards violation by the promoter of Sections 12, 14, 18 and 19 of the Act, clearly the AO will not further examine that question -- The AO will only proceed to determine the quantum of compensation or interest keeping in view the factors outlined in Section 72 of the Act -- This way the powers of the Authority under Section 31 read with Sections 35 to 37 of the Act will not overlap the functions of the AO under Section 71 of the Act. Both sets of provisions are, therefore, capable of being harmonized.

(Para 68)

O. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Sections 12, 14, 18, 19, 35, 36, 37, 71, 72 – Haryana Real Estate (Regulation and Development) Rules, 2017, Rule 28, 29 -- Compensation and payment of interest – Power of RERA Authority/ Adjudicating officer -- Amended Rules 28 and 29, or the amendments to Forms CRA and CAO are not ultra vires the Act.

(Para 69)

P. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Sections 12, 14, 18 and 19 -- Haryana Real Estate (Regulation and Development) Rules, 2017, Rule 28, 29 -- Prospective application of the amended Rules 28 and 29 of the Haryana Rules -- Change of forum would be ‘procedural’ – As long as the complaint is yet to be decided as on the date of the notification publishing the Haryana Amendment Rules 2019, that will now be decided consistent with the procedure outlined under the amended Rules 28 and 29 of the Haryana Rules -- If the Authority finds there to be a violation of Sections 12, 14, 18 and 19 of the Act by the promoter, and the complaint is by the allottee, then for determining the quantum of compensation such complaint will be referred by the Authority to the AO in terms of the amended Rule 28 of the Haryana Rules -- A complaint that has already been adjudicated prior to the coming into force of the amended Rules 28 and 29 of the Haryana, and the decision has attained finality, will not stand reopened.

(Para 72)

Q. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Sections 2 (q)(zf)(zn) – Haryana Real Estate (Regulation and Development) Rules, 2017, Rule 3,4,5,6,7,8,9,10,11,12,13,14,15,16 -- Ongoing projects – Retroactive application of the Act to ‘ongoing projects’ -- The Act is intended to apply even to ‘ongoing’ Real Estate Projects -- The expression ‘Completion Certificate’ has been defined under Section 2 (q) of the Act – The expression ‘occupancy certificate’ is defined u/s 2 (zf) of the Act – It is plain that the legislative intent was to make the Act applicable to not only to the projects which were to commence after the Act became operational but also to ongoing projects -- Court rejected the challenge to Sections 13, 18 (1) and 19 (4) of the Act and Rules 3 to 16 of the Haryana Rules as regards their retroactive applicability to ‘ongoing projects’.

(Para 73-81)

R. Real Estate (Regulation and Development) Act, 2016 (16 of 2016), Sections 2(a)(c)(o)(zn), 3(2)(b), 13, 18(1), 19(4) -- Haryana Real Estate (Regulation and Development) Rules, 2017, Rules 8, 15 -- Ongoing project – Retrospective effect – Vires of Section 13, 18(1), 19(4) of RERA Act -- Vires of Rule 8, 15 of Haryana Rules – Concept of ‘ongoing project’ is unique to the Act -- The legislature was conscious of the impact that the Act would have on such ‘ongoing projects’ -- A collective reading of Section 3 with Section 2 (o) and 2 (zn) indicates that care was taken to specify which of the projects would stand exempted -- Section 3 (2) (b) of the Act is categorical that no registration of the project would be required where “the promoter has received completion certificate for real estate project prior to the commencement of this Act.” -- It cannot thus be argued that without satisfying the above requirement or the other two contingencies in Sections 2 (a) and 2 (c) of the Act, a promoter can avoid registering an ‘ongoing’ project under the Act -- Held, Sections 13, 18 (1) and 19 (4) of the Act and Rules 8 and 15 of the Haryana Rules do not fall foul of Articles 14 and 19 (1) (g) of the Constitution on account of the their retroactive applicability to ‘ongoing’ projects.

(Para 84, 85)

37. (SC) 01-10-2020

Aircraft Act, 1934 (22 of 1934), Section 5-A, 6 -- Aircraft Rules, 1937, 133-A – Constitution of India, Article 32 -- Covid-19 pandemic situation -- Refund of Air Fare – Batch of cases disposed of with the following directions:

1. If a passenger has booked a ticket during the lockdown period (from 25th March, 2020 to 24th May, 2020) for travel during lockdown period and the airline has received payment for booking of air ticket for travel during the same period, for both domestic and international air travel and the refund is sought by the passenger against that booking being cancelled, the airline shall refund the full amount collected without any cancellation charges. The refund shall be made within a period of three weeks from the date of cancellation.

2. If the tickets have been booked during the lockdown period through a travel agent for a travel within the lockdown period, in all such cases full refund shall be given by the airlines immediately. On such refund, the amount shall be passed on immediately by the agent to the passengers.

3. Passengers who booked tickets at any period of time but for travel after 24th May, 2020 – refund of fares to the passengers covered under this category shall be governed by the provisions of Civil Aviation Requirements (CAR).

4. Even for international travel, when the tickets have been booked on an Indian carrier and the booking is ex-India, if the tickets have been booked during the lockdown period for travel within the lockdown period, immediate refund shall be made.

5. If the tickets are booked for international travel on a foreign carrier and the booking is ex-India during the lockdown period for travel within the lockdown period, full refund shall be given by the airlines and said amount shall be passed on immediately by the agent to the passengers, wherever such tickets are booked through agents. In all other cases airline shall refund the collected amount to the passenger within a period of three weeks.

6. In all other cases, the airlines shall make all endeavours to refund the collected amount to the passenger within 15 days from today. If on account of financial distress, any airline / airlines are not able to do so, they shall provide credit shell, equal to the amount of fare collected, in the name of passenger when the booking is done either directly by the passenger or through travel agent so as to consume the same on or before 31st March, 2021. It is open to the passenger either to utilize such credit shell upto 31st March, 2021 on any route of his choice or the passenger can transfer the credit shell to any person including the travel agent through whom he / she has booked the ticket and the airlines shall honour such a transfer.

6.1. The credit shell issued in the name of the passenger shall be transferable which can be utilized upto 31st March, 2021 and the concerned airline shall honour such a transfer by devising a mechanism to facilitate such a transfer. It is also made clear that such credit shell can be utilized by the concerned agent through whom the ticket is booked, for third party use. It is also made clear that even in cases where credit shell is transferred to third party, same is to be utilized only through the agent who has booked the ticket at the first instance.

7. In cases where passengers have purchased the ticket through an agent, and credit shell is issued in the name of passenger, such credit shell is to be utilized only through the agent who has booked the ticket. In cases where tickets are booked through agent, credit shell as issued in the name of the passenger which is not utilized by 31st March, 2021, refund of the fare collected shall be made to the same account from which account amount was received by the airline.

8. In all cases where credit shell is issued there shall be an incentive to compensate the passenger from the date of cancellation upto 30th June, 2020 in which event the credit shell shall be enhanced by 0.5% of the face value (the amount of fare collected) for every month or part thereof between the date of cancellation and 30th June, 2020. Thereafter the value of the credit shell shall be enhanced by 0.75% of the face value per month upto 31st March, 2021.

Further, the Directorate, shall ensure strict compliance of the directions referred above, by issuing necessary instructions to the all concerned.

(Para 19)

40. (SC) 24-08-2020

A. Consumer Protection Act, 1986 (68 of 1986), Section 2(1)(o) – Apartment/ Flat developer -- Deficiency in service -- Failure of the developer to comply with the contractual obligation to provide the flat to a flat purchaser within a contractually stipulated period amounts to a deficiency -- Expression “service” in Section 2 (1) (o) means a service of any description which is made available to potential users including the provision of facilities in connection with (among other things) housing construction.

(Para 24)

B. Consumer Protection Act, 1986 (68 of 1986), Section 14(1)(e) – Apartment/ Flat developer – Unfair bargain -- Power of Consumer Courts -- Flat purchasers make legitimate assessments in regard to the future course of their lives based on the flat which has been purchased being available for use and occupation -- These legitimate expectations are belied when the developer is guilty of a delay of years in the fulfilment of a contractual obligation -- There has been a gross delay in the handing over of possession beyond the contractually stipulated debt -- Jurisdiction of the consumer forum to award just and reasonable compensation as an incident of its power to direct the removal of a deficiency in service is not constrained by the terms of a rate which is prescribed in an unfair bargain.

(Para 24)

C. Consumer Protection Act, 1986 (68 of 1986), Section 12 – Compensation for delayed possession – Execution of conveyance deed and handing over possession – Effect of -- Developer has undertaken to provide a service in the nature of developing residential flats with certain amenities and remains amenable to the jurisdiction of the Consumer Fora – Court did not subscribe the view of the NCDRC that flat purchasers who obtained possession or executed Deeds of Conveyance have lost their right to make a claim for compensation for the delayed handing over of the flats.

(Para 36)

D. Consumer Protection Act, 1986 (68 of 1986), Section 12 – Delay in possession -- Re-sale of apartment by allottee – Subsequent buyer – Rights of -- Appellants transferred their title, right and interest in the apartments would not be entitled to the benefit since they have sold their interest in the apartments to third parties -- It cannot be said that the subsequent transferees suffered any agony and harassment comparable to that of the first buyers, as a result of the delay in the delivery of possession in order to be entitled to compensation.

(Para 38)

E. Consumer Protection Act, 1986 (68 of 1986), Section 12 – Purchase of Apartment/ Flat -- Amenities -- Flat purchasers cannot be left in the lurch or be told that the absence of facilities which were to be provided by the developer is compensated by other amenities which are available in the area -- Developer must be held accountable to its representation -- Representation held out by the developer cannot be dismissed as chaff -- Difficult for the court to quantify the exact nature of the compensation that should be provided to the flat buyers -- Difficulties in determining the measure of compensation cannot however dilute the liability to pay -- A developer should be held accountable to the process of law -- To allow the developer to escape their obligation would put a premium on false assurances and representations made to the flat purchasers -- Dismissal of the complaint by the NCDRC was erroneous.

(Para 43-55)

48. (SC) 02-04-2019

A. Consumer Protection Act, 1986 (68 of 1986), Section 23 -- Purchase of flat – Unfair terms and conditions – Effect of -- Terms of the Apartment Buyer’s Agreement were wholly one-sided and unfair to the Respondent/ Flat Purchaser – Appellant/ Builder could not seek to bind the Respondent with such one-sided contractual terms.

(Para 7)

B. Consumer Protection Act, 1986 (68 of 1986), Section 23 -- Haryana Real Estate (Regulation and Development) Rules, 2017, Rule 15 -- Delayed possession of flat – Refund with interest – Right of Flat purchaser –Appellant/ Builder failed in obtaining the Occupancy Certificate and offering possession of the flat to the Respondent/ Purchaser within the time stipulated in the Agreement, or within a reasonable time thereafter – Respondent/ Flat Purchaser could not be compelled to take possession of the flat, even though it was offered almost 2 years after the grace period under the Agreement expired – Respondent/ Flat Purchaser held entitled for refund of the entire amount deposited by him with Interest – National Commission rightly awarded Interest @10.7% S.I. p.a. by applying Rule 15 of the Haryana Real Estate (Regulation And Development) Rules, 2017 from the date of each installment till 05.02.2017 i.e. till the date after which the Order of stay of cancellation of the allotment was passed; and thereafter, from the date of the Commission’s final Order till the date on which the amount is refunded with Interest -- Civil Appeals dismissed, and the Final Judgment and Order passed by the National Consumer Disputes Redressal Commission affirmed.

(Para 8-10)